This process is for generators greater than 20 megawatts (MW).
1. 皇冠现金盘公司LGIP申请日期:10月. 2, 2023
- hg8868皇冠下载 submitted its required Compliance Filing with FERC Order 2023 (ER24-10-000). 这份文件可以在皇冠现金盘公司的 绿洲 in the Recent Filings subfolder contained in the Tariff Folder.
- Large Generation Interconnection Procedures (LGIP)
2. 申请后30个日历日:11月11日. 1, 2023
- In accordance with FERC Order 2023 and Section 5.皇冠现金盘公司LGIP合规文件1, any Interconnection Customer assigned a Queue Position as of 11:59:59 p.m. (MT) on November 1, 2023 (i.e., 10月2日之后的30个日历日, 2023 filing date) shall retain that Queue Position subject to the requirements in Sections 5.1.1, 5.1.1.1和5.1.1.2 .已归档的LGIP.
- Interconnection Requests submitted after this date will not be eligible to proceed into the transition process and can be submitted in the initial Cluster Request Window, as described in Section 3.4.1 .已归档的LGIP.
3. Commission Approved Effective Date (CAED): Requested Jan. 1, 2024
- hg8868皇冠下载 shall offer the Transitional Cluster Study Agreement (Appendix 7) 不迟于CAED,按第5节规定.1.1.2的LGIP.
4. CAED后60天:2024年3月1日
- Applicable Transitional Cluster Study documents, data and deposit due.
- 过渡聚类研究提交清单
5. Interim Transitional Cluster Study Report (TCSR): July 19, 2024
- Interconnection Customer shall have 30 Calendar Days to comment on the Interim TCSR once it has been received.
6. 最终过渡性群集研究报告:12月. 26, 2024
- After the Final TCSR is issued, Interconnection Customer shall proceed pursuant to Section 1LGIP的1 to enter into a 大型发电机互联协议.
1. 皇冠现金盘公司LGIP申请日期:10月. 2, 2023
- hg8868皇冠下载 submitted its required Compliance Filing with FERC Order 2023 (ER24-10-000). 这份文件可以在皇冠现金盘公司的 绿洲 in the Recent Filings subfolder contained in the Tariff Folder.
- Large Generation Interconnection Procedures (LGIP)
2. 申请后30个日历日:11月11日. 1, 2023
- In accordance with FERC Order 2023 and Section 5.皇冠现金盘公司LGIP合规文件1, any Interconnection Customer assigned a Queue Position as of 11:59:59 p.m. (MT) on November 1, 2023 (i.e., 10月2日之后的30个日历日, 2023 filing date) shall retain that Queue Position subject to the requirements in Sections 5.1.1, 5.1.1.1和5.1.1.2 .已归档的LGIP.
- Interconnection Requests submitted after this date will not be eligible to proceed into the transition process and can be submitted in the initial Cluster Request Window, as described in Section 3.4.1 .已归档的LGIP.
3. Commission Approved Effective Date (CAED): Requested Jan. 1, 2024
- hg8868皇冠下载 shall offer the Transitional Serial Interconnection Facilities Study Agreement (Appendix 8) 不迟于CAED第5节规定的时间.1.1.LGIP的1.
4. CAED后60天:2024年3月1日
- Applicable Transitional Serial Study documents, data and deposit due.
- 过渡性系列研究提交清单
5. Transitional Serial Facilities Study Report (TFSR): May 30, 2024
- After the Final TFSR is issued, Interconnection Customer shall proceed pursuant to Section 11 of this LGIP to enter into a 大型发电机互联协议.
1. Eligibility Requirements
回顾第3节中的全部需求.4.2的LGIP.
- Large Generation Interconnection Procedures (LGIP)
- $5,000不可退还的申请费
- 研究存款
- $35,000 plus $1,000 per MW for Interconnection Requests ≥ 20 MW < 80 MW
- $150,000 for Interconnection Requests ≥ 80 MW < 200 MW
- ≥200mw的互连请求为250,000美元
- Commercial Readiness Deposit equal to two times the study deposit
- LGIP互连应用
- 90%的现场控制概述在 商业行为
- 数据要求类似于 过渡聚类研究提交清单
2. 集群请求窗口:45日历天
The first Cluster Request Window shall open March 1, 2025.
- 集群请求窗口将于每年3月1日开放.
- Interconnection Requests submitted outside of this time will not be considered.
3. 客户参与窗口:60日历天
- 视图 绿洲 to view the application list.
4. 聚类研究:150日历天
Evaluates the impact of the proposed interconnection on the reliability of the Transmission System. Consists of power flow, 稳定, and short circuit analyses as well as provides a list of facilities that are required.
5. 群集研究重新研究:150日历天
如果重新研究是必要的, hg8868皇冠下载 will notify the Interconnection Customers within 30 Calendar Days after the Cluster Study Report Meeting. If there are no withdrawals after the completion of the Cluster Study or Restudy, 或者认为没有必要重新研究, hg8868皇冠下载 will notify the Interconnection Customers within 30 Calendar Days of such determination.
- 持续地盘控制的示范
- Bring Commercial Readiness Deposit to 5% of Interconnection Customer’s Network Upgrade costs assigned in the Cluster Study.
6. 设施研究:90-180日历日
Shall be specific to each Interconnection Request and be preformed on an individual basis
- LGIP Facilities Study Agreement
- 100%现场控制,如 商业行为
- Bring Commercial Readiness Deposit to 10% of Interconnection Customer’s Network Upgrade costs assigned in the Cluster Study or Cluster Restudy.
7. 大型发电机互联协议
All projects greater than 20 MW are subject to technical requirements under the LGIA.
- 大型发电机互联协议
- 持续地盘控制的示范
- Deposit equal to 20% of Interconnection Customer’s estimated Network Upgrade costs assigned in the Draft LGIA minus the total amount of Commercial Readiness Deposits previously provided.